A dry dock cost breakdown starts with one uncomfortable fact: the yard quote is only part of what a docking costs, and it is rarely the part that overruns. For a Fleet Manager approving a project of $500,000 to $3 million or more, the real question is where money goes, where it leaks, and how much reserve to hold. This guide splits the cost into buckets, shows the seven leaks that push budgets up, and sets out contingency and control methods you can apply to the next dock.

BUDGET DRIFT
From $1.0M Approved to $1.25M Final: Where the Extra 25% Hides
An illustrative docking drifting to the top of the 15 to 25% overrun range. Each step is a leak you can plan for.
$1.0M

Approved budget
+12%

Scope growth
+7%

Steel findings
+4%

Extra days
+2%

Class items
$1.25M

Final cost
Illustrative example, our own. Free trial available. Or book a walkthrough built around your own docking budget.
Updated · About 11 minutes to read · For Fleet Managers and dock budget owners
KEY TAKEAWAYS
  • Budget six yard and owner cost buckets, and track off-hire as a separate commercial cost.
  • Most overrun comes from seven leaks: late scope, discovery items, extra days, mid-dock rates, mandatory retrofits, material prices and soft costs.
  • Marine Inspection's guide recommends 10 to 15% contingency. Use it for discoveries and control scope growth with a freeze date.
  • One extra day of off-hire can equal several percent of the direct budget, so price every variation in days as well as dollars.
  • Reported overrun figures differ by source, from 10 to 15% to 15 to 25%. We found no independent public statistic.

Dry Dock Cost Breakdown: Where the Money Goes

Direct dry dock cost runs from $500,000 to more than $3 million in Marine Inspection's dry docking guide, depending on vessel size and scope. Inside that figure, a ship repair cost tool published by Ship Universe groups spending into six buckets, which is a practical way to build and review a budget line by line.

Six dry dock cost buckets and what moves each one
Cost bucketWhat it coversWhat drives itVariable to watch
Yard daily charges Dock hire, mobilisation, services Fixed by yard tariff and days in dock Dock days
Hull cleaning and coating Blasting, surface preparation, paint system Area, coating spec, weather Area and paint spec
Steel renewal Plate and structural repairs Wastage found at inspection Gauging results
Machinery and propulsion Engine, shaft, rudder, valves, pumps Overhaul scope and spares Running hours and condition
Class, survey and statutory Surveys, tank tests, certificates Dictated by the survey window Class items due
Owner supplies and logistics Spares, crew, superintendent, travel Lead times and freight Long-lead items
Bucket structure follows the Ship Universe drydock cost tool. Which bucket is largest depends on ship type, yard and scope.

Marine Inspection's guide also gives upper-end ranges by work stream: hull and structure $100,000 to $800,000 or more, machinery systems $80,000 to $500,000 or more, underwater components $50,000 to $300,000, tank inspections $40,000 to $200,000, and safety equipment and statutory work $30,000 to $150,000. Hull and structure is the widest range because it holds steel renewal, the least predictable item. Our dry dock planning timeline guide shows when each of these decisions has to be made.

$0.5M to $3M+
Direct cost
Vessel size and scope dependent, per Marine Inspection's guide.
30 to 50%
Chinese vs Korean price gap
Chinese and regional yards typically run below Korean pricing, per the same guide.
2 to 3x
Mid-dock scope gap rate
Gaps found after contract typically cost 2 to 3 times the pre-tender rate.
10 to 15%
Suggested contingency
The reserve Marine Inspection's guide recommends in budget approval.

Yard Cash vs Commercial Cost

Ship Universe's calculator makes a distinction worth copying: lost contribution per day is a commercial opportunity cost, not yard cash. Keep the two apart in your budget. Yard cash is what the yard and suppliers invoice. Commercial cost is what the ship does not earn while it sits in dock.

Why the split matters

  • Different owners. The Technical Superintendent controls most yard cash. The commercial team owns the off-hire assumption.
  • Different levers. Yard cash is reduced through scope and tender discipline. Commercial cost is reduced by fewer days.
  • Different exposure. Marine Inspection's guide puts off-hire beyond the planned duration at $20,000 to $50,000 per day. Another guide quotes $20,000 to $100,000 depending on ship type. A balancia article uses a container ship at $30,000 a day, so a five-day extension costs $150,000 in lost income before any repair bill.

A useful habit is to state every variation order in two numbers: the repair cost and the days it adds. The second number often decides whether the work is approved.

Seven Dry Dock Cost Leaks and How to Seal Them

Reading the sources together, overruns come from a short list of causes rather than from random bad luck. Each one has a point where it can be caught earlier.

1Late scope additions
LEAKThe work list grows 20 to 30% between contract and arrival, mostly from late technical additions, according to one vendor article.
SEAL ITSet a scope freeze date, and treat every later item as a variation order.
2Discovery items
LEAKCorrosion in ballast tanks or wastage found only after blasting or opening up.
SEAL ITGauge early, price steel as a unit rate in the tender, and hold a steel contingency.
3Extra days in dock
LEAKOne bulk carrier example added 10 days after serious ballast tank corrosion was found.
SEAL ITPrice every extra day at your own off-hire figure before approving work.
4Mid-dock rates
LEAKScope gaps found after the contract typically cost 2 to 3 times the pre-tender rate, per Marine Inspection's guide.
SEAL ITClose the gaps in the specification before tender, not in dock.
5Mandatory retrofits
LEAKBallast water treatment retrofits and replacement of outdated firefighting equipment cannot be deferred.
SEAL ITList regulatory deadlines in the plan 12 months out.
6Material price moves
LEAKSteel prices can rise between budget and repair, and the repair still has to be done.
SEAL ITFix steel prices in the contract and agree an escalation clause.
7Soft costs
LEAKCrew accommodation, waste disposal, and idle time sit outside yard invoices.
SEAL ITAdd them as owner cost lines from day one.
Leaks are drawn from the sources named on this page. The seal actions are our suggestions.
Overrun, Scope Growth and Contingency Figures by Source (Percent)
Scope growth, contract to arrival

20 to 30%
Overrun without project management

15 to 25%
Overrun in another vendor article

10 to 15%
Suggested contingency in budget approval

10 to 15%
Overrun for owners who freeze scope and assign decisions

Within 3%
Bars are scaled to the largest figure, 30%, using the upper end of each range. Figures come from Marine Inspection's dry docking guide and an iShipPlus article, both from software vendors. We did not find an independent public statistic, so treat these as indicative.

The sources disagree on the typical overrun: 15 to 25% in one guide and 10 to 15% in another. The point is not which is right. It is that both are large enough to justify the controls below.

Catch Cost Leaks Before the Invoice
Track estimated, committed, actual and forecast cost against the dock plan every day, with evidence attached to each variation.
Free trial available. Or book a walkthrough built around your own docking budget.

Dry Dock Contingency: How Much to Hold and What It Is For

Marine Inspection's guide recommends 10 to 15% contingency in the budget approval. That is a sound starting point, but the number matters less than what the reserve is allowed to pay for. If it covers scope that should have been frozen, it will be gone before the first tank is opened.

A risk-tiered approach

We suggest setting the reserve by how likely the ship is to produce discovery items. The tiers below are our own, anchored to the 10 to 15% baseline. The higher tier goes above it because older ships with open scope can exceed it, so adjust the figures to your own history.

Suggested contingency by risk tier
Risk tierTypical profileContingencyMost likely call on it
Lower risk Younger ship, recent thickness gauging, clean tank history, scope frozen About 10% Mostly small discoveries and days
Typical Mid-life ship, some coating breakdown, normal class items About 12% Steel and coating area growth
Higher risk Older ship, known corrosion, no recent gauging, open scope 15% or more, with steel held separately Steel renewal and extra days
Our suggested framework, not an industry standard. Record each tier decision in the budget approval so the reasoning survives to the post-dock review.

Five Controls That Prevent Dry Dock Budget Overrun

Marine Inspection's guide lists the controls that reduce typical overruns. We have grouped them into five actions, and added a vendor-sourced scope trio.

  • Specification first. A comprehensive pre-dock specification closes the gaps that cost 2 to 3 times more in dock.
  • Line-by-line tender analysis. Compare yards on every item, not the total, and check variation order rates.
  • Real-time cost tracking. Compare spend with the Gantt plan daily so the forecast moves before the invoice does.
  • Change order control. Require evidence for every variation, with a price, a time impact and a named approver.
  • A contract framework. The guide points to the BIMCO RepairCon framework for dispute resolution.

Scope freeze, single owner, decision matrix

An iShipPlus article, from a software vendor, recommends three structural fixes: freeze work scope four weeks before arrival and treat later additions as change orders, name one accountable owner for parts as critical path, and give on-site representatives a decision matrix with approval authority and response times. The article claims owners who do all three routinely finish within 3% of budget. We could not verify that figure independently, but the logic is consistent with the leaks above.

Variation Order Approval Ladder

Slow decisions cost days, and uncontrolled decisions cost money. An approval ladder fixes both by saying who can approve what, and how fast. The thresholds below are our illustrative template. Set yours against the size of your own budgets.

Illustrative variation order approval ladder
ApproverVariation sizeWhat is required
Dock superintendent Up to 0.5% of approved budget Same-day approval, recorded with photos and price
Technical Superintendent 0.5% to 2% Written variation order with time impact
Fleet Manager 2% to 5% Business case: cost, days, risk of deferral
Fleet Manager and finance or owner Above 5% Reforecast and re-approval of the project budget
Our suggested template. Percentages are of the approved direct budget, and cumulative variations should be tracked as well as single items.

Worked Example: A Contingency Tested by Three Findings

This example is our own and uses assumed figures. Take a $1,000,000 direct budget with 12% contingency, and an assumed off-hire of $35,000 per day. In dock the team finds a tank steel repair, needs three extra days, and meets a late regulatory item.

Illustrative budget position after three findings
LineAmount
Approved direct budget $1,000,000
Contingency at 12% $120,000
Authorised total $1,120,000
Steel finding in tank $60,000
Three extra dock days at $35,000 off-hire $105,000
Late regulatory item $20,000
Total unplanned $185,000
Position against authorised total $65,000 over
Position against base budget 18.5% over
Assumed figures, our own. Replace them with your yard quote and your own commercial day rate.

Two lessons come out of it. First, the extra days cost more than the steel, so schedule discipline protects more money than a tough steel rate. Second, one extra day at $35,000 is 3.5% of the direct budget, which means a few days can consume a large part of the reserve before the repair bill is counted.

After the Dock: Benchmark Cost and Feed the Next Budget

Shipnet's article on dry docking challenges recommends tracking line-item costs and benchmarking performance across similar vessels. That only works if each project records the same lines. At close-out, reconcile final cost against budget by bucket, list every variation with its cause, and record what the original specification missed.

What to carry into the next dock

  • Steel quantity found against steel quantity budgeted, by tank.
  • Extra days by cause: weather, parts, scope or yard performance.
  • Variation orders by size and by who approved them.
  • Rates actually paid compared with the tender.
  • Defects raised on the post-dock list, with owners and deadlines.

These records improve contingency sizing for the next ship in the same class, and they give you evidence for tender negotiations. Our guide to dry dock preparation in China and the equivalent guide for South Korea show how regional differences in yard practice can affect these lines.

Common Dry Dock Budgeting Mistakes

1
Contingency used for scope growth
A 10 to 15% reserve is meant for discoveries. If scope keeps growing, it disappears before steel is found.
2
Only yard cost in the budget
Off-hire, crew, waste and owner supplies do not appear on the yard quote but they are part of the real cost.
3
Comparing yards on headline price
Marine Inspection's guide says Chinese and regional yards run 30 to 50% below Korean pricing, but variation order rates and delivery record matter as much.
4
No decision authority in dock
When the owner's representative cannot approve a deviation, the ship sits idle while emails cross time zones.
5
Cost known only at the final invoice
Without daily forecast to completion, the overrun is a surprise rather than a decision.
6
No lessons recorded
Cost and defect data stay in one project instead of improving the next specification.

Systems for Dry Dock Cost Control

Cost control in dock depends on seeing the forecast daily and on keeping evidence behind every variation. Marine Inspection supports specification development with version control, distribution of the yard document package, daily progress tracking with Gantt charts, real-time cost monitoring, dated photos linked to findings and digitisation of the post-dock defect list, as described in its own dry docking guide. Finding records with owners, deadlines and evidence make variation orders easier to approve and to audit later.

Frequently Asked Questions About Dry Dock Costs

How much does a dry docking cost?

Marine Inspection's dry docking guide gives direct costs of $500,000 to more than $3 million, depending on vessel size and scope. Off-hire, crew costs and owner supplies come on top of the yard figure.

What are the main dry dock cost components?

Yard daily charges, hull cleaning and coating, steel renewal, machinery and propulsion work, class and statutory items, and owner supplies and logistics. Off-hire is a commercial cost that sits beside them.

How much contingency should a dry dock budget include?

Marine Inspection's guide recommends 10 to 15% in the budget approval. Our own suggestion is to size it by risk tier and to hold steel separately for older ships, and to control scope growth through a freeze date instead of spending the reserve on it.

Why do dry dockings run over budget?

The causes seen across the sources we reviewed are late scope additions, discovery items such as corrosion, extra days, mandatory retrofits, material price moves, and slow decisions in dock.

How much does an extra day in dock cost?

It depends on the ship. Marine Inspection's guide gives $20,000 to $50,000 per day in off-hire beyond the planned duration, another source quotes up to $100,000 for larger ships, and a container ship example uses $30,000. Use your own commercial figure.

How do you stop scope creep in dry dock?

Freeze the scope before arrival, route later additions through variation orders with a price and a time impact, and agree who can approve what. One vendor article suggests freezing four weeks before arrival.

Are Chinese yards cheaper than Korean yards for dry docking?

Marine Inspection's guide says Chinese and regional yards typically run 30 to 50% below Korean pricing, with Korean yards at the premium end. Compare variation order rates, capacity and track record on similar ships as well as the headline price.
Close Every Dock Within Budget
One place for specifications, variation orders with evidence, daily cost against plan and the post-dock defect list across your fleet.
Free trial available. Or book a walkthrough built around your own docking budget.