A dry dock planning timeline of 6 to 12 months is the difference between a docking that finishes on time and on budget and one that drifts into extra days and extra cost. For a Technical Superintendent, the dock is the largest single project of the ship's maintenance cycle, and most of its outcome is decided long before the ship reaches the yard. This guide sets out the six phases month by month, the budget and scope controls that hold the cost, the class drivers behind the schedule, and the gate reviews that keep the project honest. Start a free trial of Marine Inspection to run the dock project from one place.

DOCK PROJECT PLAN
Twelve Months to Undocking: What Must Be Decided and When
The six dry dock phases laid out against the months before the ship enters the dock.
Phase
M-12
M-11
M-10
M-9
M-8
M-7
M-6
M-5
M-4
M-3
M-2
M-1
Dock
After
When
1Planning and strategy

6 to 12 months before
2Specification

4 to 6 months before
3Tender and yard selection

3 to 5 months before
4Pre-arrival preparation

1 to 3 months before
5Execution in dock

Dock period
6Close-out

After undocking
Free trial available. Or book a walkthrough built around your own fleet.
Updated · About 11 minutes to read · For Technical Superintendents and docking teams
KEY TAKEAWAYS
  • Plan 6 to 12 months ahead, and start condition assessment even earlier for large programmes.
  • The specification is the most important document. Write it early, with a clear split between must-do and deferrable work.
  • Scope creep is the most consistent cost control challenge. Set a scope freeze date and rules for variation orders.
  • Track estimated, committed, actual and forecast cost every day in dock.
  • Marine Inspection's dry dock guide puts overruns at 15 to 25% without systematic project management, a figure we could not confirm independently.

Why Dry Dock Planning Starts 6 to 12 Months Early

A dry docking combines compulsory survey work, hull coating, machinery overhaul and sometimes steel renewal in a short, expensive window. Yards sell slots in advance, specialist contractors and spares have lead times, and class surveyors must be booked. Starting late reduces your bargaining power and pushes scope decisions into the dock, where every extra item costs more.

What drives the dock window

  • Class and flag intervals. Under the UK guidance we reviewed, a ship needs two bottom inspections in any five-year period, no more than 36 months apart, with one out of the water.
  • Charter commitments. Docking in a charter gap or a seasonal low can limit off-hire cost.
  • Condition of the ship. Equipment trends and outstanding defects decide what has to be done this time.
  • Yard availability. Marine Inspection's guide notes that Korean yards in particular need advance booking.

How long a dry docking takes

Marine Inspection's guide gives 5 to 21 days as typical. Other sources put intermediate dockings at 10 to 21 days and special surveys at 20 to 30 days or more, with unexpected repairs adding 5 to 15 days. Duration depends heavily on the amount of steel and machinery work, which is why scope control matters.

The Six-Phase Dry Dock Timeline

Dry dock phases, timing, outputs and the key decision
PhaseTimingMain outputsKey decision
1. Planning and strategy 6 to 12 months before Docking window, budget, off-hire assumption, condition assessment Which survey window and which charter gap?
2. Specification 4 to 6 months before Work list with class items, must-do and deferrable split What is in scope and what is deferred?
3. Tender and yard selection 3 to 5 months before Bids compared, yard slot booked, contract terms Which yard, at what price and slot?
4. Pre-arrival preparation 1 to 3 months before Spares ordered, documents sent, underwater inspection, crew plan Is the scope frozen and the ship ready?
5. Execution In dock Daily progress and cost tracking, controlled variation orders Do we approve extra work or defer it?
6. Close-out After undocking Defect list, final cost reconciliation, lessons learned What goes into the next docking?
Phase timings follow Marine Inspection's dry docking guide. Another ship management source describes a longer sequence for large programmes: condition assessment 18 or more months ahead, specification 12 months, tendering 8 to 10 months, pre-dock preparation 6 months and logistics 3 months. Choose the schedule that fits your fleet and yard market.

Dry Dock Planning, Phase by Phase

Phase 1: Planning and strategy (6 to 12 months before)

Set the objectives: which survey window, which charter gap, what budget and what off-hire assumption. Use condition data, such as equipment trends, outstanding maintenance and deficiencies, to build a first list of likely work. Agree who owns the project and who approves changes.

Phase 2: Specification (4 to 6 months before)

The specification defines the work scope, the acceptance standards and the inspection requirements the yard will price and deliver. Include class and flag items, then mark each remaining item as must-do or deferrable. Decide early which high-cost materials you will supply yourself, since owner-furnished materials can control cost.

Phase 3: Tender and yard selection (3 to 5 months before)

Issue the specification to a short list of yards, compare bids line by line and confirm the slot. Price is only one factor. Check the yard's capacity, past performance on similar ships and its approach to variation orders. Marine Inspection's guide reports that Chinese and regional yards can run 30 to 50% below South Korean pricing, so the trade-off between price, location and quality needs a conscious decision.

Phase 4: Pre-arrival preparation (1 to 3 months before)

Freeze the scope, order long-lead spares, send the yard its document package (30 to 60 days before arrival, per the guide), carry out underwater inspection and agree the crew and superintendent plan. A ship that arrives with the scope frozen and the spares on site gives the yard little room to delay.

Phase 5: Execution in dock

Run daily progress and cost reviews against the plan. Hold every extra item to a variation-order process with a stated price, a time impact and a clear approve-or-defer decision. Maintain inspection records as the work proceeds.

Phase 6: Close-out

Reconcile final cost against budget, issue the post-dock defect list, and record what surprised the team. Feed those lessons into the next dock specification and the planned maintenance system.

Keep Every Dock Phase on Schedule
Track specifications, yard packages, daily progress and cost against budget in one place, from first plan to final defect list.
Free trial available. Or book a walkthrough built around your own fleet.

Budget and Overrun Control

$0.5M to $3M+
Direct cost
Depends on vessel size and scope, per Marine Inspection's guide.
$20K to $100K
Off-hire per day
$20,000 to $50,000 in one guide and up to $100,000 in another, depending on ship type and market.
$200K to $1M
Steel renewal found in dock
Extra cost range one source gives for steel renewal discovered during inspection.
15 to 25%
Typical overrun, unmanaged
Marine Inspection's figure for dockings without systematic project management.
Work Stream Cost Ranges (Upper Bound, USD Thousands)
Hull and structure

$100K to $800K+
Machinery systems

$80K to $500K+
Underwater components

$50K to $300K
Tank inspections

$40K to $200K
Safety equipment

$30K to $150K
Upper end of each range in Marine Inspection's dry docking guide. Bars are scaled to the largest, hull and structure at $800K. Actual costs depend on yard, ship type and scope.

Four cost numbers to track every day

  • Estimated cost: the approved budget.
  • Committed cost: purchase orders and subcontracts placed.
  • Actual cost: invoices and labour incurred.
  • Forecast to completion: your best view of the final figure.

These four baselines, described in a ship repair project cost article, show the gap between what you planned, what you have committed and where you are heading. A rising forecast is the early warning that an overrun is coming.

Worked example (our own, illustrative). If extra work adds 5 days at an assumed $35,000 of off-hire per day, the delay costs $175,000 before any repair cost. Use your own daily figure when you build the business case for a tighter scope.

Scope Management: Must-Do, Deferrable and Opportunistic

Scope creep is the most consistent cost control challenge. It comes from work added in dock for unforeseen conditions and from opportunistic additions that seemed small. A simple three-way split controls both.

MUST DO
Class, flag and safety
Survey items, statutory work and safety-critical defects. Always in the specification.
DEFERRABLE
Condition-based work
Items that can wait to the next window if time or budget runs short. Record the decision and the risk.
OPPORTUNISTIC
Nice-to-have additions
Needs a business case. Approve only if it saves time or cost later.
Our suggested framework. Add a scope freeze date about one to two months before arrival and a named approver for every variation order.

Class and Flag Drivers Behind the Schedule

Bottom inspection requirements, UK guidance summary
RequirementWhat it saysSource
Two bottom inspections in any five years Maximum interval between them 36 months UK MGN 217, for ships under SOLAS and the Load Line Convention
One out-of-water One inspection must be out of the water, ideally with the renewal survey UK MGN 217
In-water survey for intermediate inspections Allowed where a dry-dock survey is not required UK MGN 217
Ships over 15 years In-water survey needs special consideration. Oil tankers and bulk carriers over 15 years under the Enhanced Survey Programme are not eligible UK MGN 217
Summarised from UK Maritime Guidance Note MGN 217. Your class society and flag state set the exact rules for your ship, so confirm them before fixing the window.

Gate Reviews: Six Checkpoints for the Dock Project

1
Gate 1: Plan
Window, budget and strategy approved
Month -12 to -6
2
Gate 2: Specification
Scope issued for tender, deferrals recorded
Month -6 to -4
3
Gate 3: Award
Yard chosen, contract signed, slot confirmed
Month -4 to -3
4
Gate 4: Scope freeze
Final scope, spares on order, documents sent
Month -2 to -1
5
Gate 5: Undock
Works signed off, class items closed, trials planned
End of dock
6
Gate 6: Close
Costs reconciled, defect list issued, lessons logged
After undocking
Our suggested gate structure. Hold a short review at each gate and record the decision, the owner and any open risk.

Common Dry Dock Planning Mistakes

1
Specification written late
A rushed work list means vague scope, loose bids and more extra work in dock.
2
No freeze date
Scope that keeps growing is the most consistent cost control challenge in dock projects.
3
Spares ordered after award
Long-lead items arriving late stop work and extend the stay.
4
No daily cost view
Without actuals against budget each day, overruns are discovered only at the final invoice.
5
Hidden work not budgeted
Steel renewal and corrosion repairs found in dock can add hundreds of thousands of dollars.
6
Lessons not recorded
The same surprises return at the next docking when nothing is written down.

Systems for Dry Dock Projects

Spreadsheets and email can hold a dock plan, but they strain under version control, yard document packages and daily cost tracking. Marine Inspection supports specification development with version control, distribution of the yard documentation package, daily progress tracking with Gantt charts, real-time cost monitoring and digitisation of the post-dock defect list, as described in its own dry docking guide. Book a walkthrough to see a dock project from specification to defect list.

Frequently Asked Questions About Dry Dock Planning

How long before dry docking should planning start?

Marine Inspection's dry dock guide puts the planning window at 6 to 12 months before docking, with Korean yards especially needing advance booking. Larger technical managers may start condition assessment 18 months or more ahead, as one ship management source describes.

What are the phases of a dry dock project?

Six phases: planning and strategy, specification development, tendering and yard selection, pre-arrival preparation, execution in dock and close-out after undocking.

How long does a dry docking take?

Marine Inspection's guide gives 5 to 21 days as typical. Another source puts special survey dockings at 20 to 30 days and intermediate ones at 14 to 20 days, and says unexpected repairs can add 5 to 15 days.

How much does dry docking cost?

Marine Inspection's guide gives direct costs of $500,000 to over $3 million, depending on vessel size and scope. Off-hire adds roughly $20,000 to $50,000 per day beyond the plan in that guide, while another source quotes $20,000 to $100,000 per day depending on ship type and market.

Do dry docks really run over budget?

Marine Inspection's guide says budgets typically overrun by 15 to 25% without systematic project management. We did not find an independent public statistic for this figure, so measure your own projects.

How often must a ship be dry docked?

Under the UK guidance we reviewed, a ship needs two bottom inspections in any five-year period with no more than 36 months between them, with one out of the water. In-water surveys may be used for the intermediate one where permitted. Check your class society and flag state.

What is the most important document in dry dock planning?

The specification. One ship management guide calls it the most important document the technical manager produces, because it defines the scope, acceptance standards and inspection requirements that the yard prices and delivers.
Finish the Dock on Time and on Budget
One system for specifications, yard packages, daily progress, cost tracking and close-out across every docking in the fleet.
Free trial available. Or book a walkthrough built around your own fleet.