A liner wear reading means little on its own, and a wear reading taken at different points from the last one means even less. How should cylinder liner wear measurement be done, what do maker and trade sources say about rates and limits, and what should a Chief Engineer be able to show at the next overhaul or survey? This guide covers cylinder liner wear measurement and inspection on two-stroke engines in detail, with notes for four-stroke engines where sources exist. It draws on MAN Energy Solutions service letters, a 2026 report on Everllence guidance, a vendor measurement service and two trade or engine websites, and it flags where those disagree. For engine room routines, see our engine room maintenance tracking.


Measure the Liner the Same Way Every Time, and the Trend Tells You the Rest
Calibration points, wear rates, scavenge port checks and the records that make wear comparable.
Free trial available. Or book a walkthrough built around your own engine overhaul and liner wear records.

Where to Measure Cylinder Liner Wear: Levels, Directions and the Causes Behind Each Zone

The wear pattern depends on the zone, so the readings must be taken in the same zones

Liner wear is not uniform. A Marine Insight trade article says wear is greatest in the top third of the liner where temperature and pressure are highest, that abrasion by hard particles such as catalytic fines is worst at the dead centres, and that sulphuric acid corrosion is worst in the lower liner, producing a clover-leaf pattern. It lists friction between rings and liner, corrosion, abrasion and scuffing from insufficient lubrication as the main causes. The article is secondary, so check it against your maker's manual. The diagram shows the zones.

Where Liner Wear Concentrates and What Causes It: A Schematic of a Two-Stroke Liner (Our Drawing from Trade and Maker Sources; Not to Scale)
TDC
Upper third
Middle
Lower liner
Ports
TDC and upper third. Highest temperature and pressure. A trade article says wear is greatest in the top third, with abrasion by hard particles such as catalytic fines worst at the dead centres.
Middle. Ring sliding speed is highest here. Wear is usually lower, so a rise in the middle readings is worth noting.
Lower liner. A trade article says sulphuric acid corrosion is worst here, giving a clover-leaf pattern. Low-load running without matching the cylinder oil feed worsens it.
Scavenge ports. The place to look, not measure. Port inspection shows ring and liner condition without lifting the piston.
Zones and causes are summarised from a Marine Insight trade article, which is secondary, and from MAN Energy Solutions service letters on two-stroke engines. The middle-zone comment is our reading of ring speed, not a quoted claim. Your engine maker's manual sets the actual measuring levels.

How to Measure Cylinder Liner Wear: Tool, Temperature, Points and Directions

Calibration: the same points, the same tool, the same temperature

The two sources that describe the method agree on the essentials. Use an internal micrometer, which an engine website says should be accurate to 0.01 mm, with a flat or template bar hung down the liner and holes drilled at each reading level so every measurement is repeated at the same place. Take readings port to starboard and forward to aft, because wear is not uniform, and take more readings near the top where wear is highest. Both the liner and the micrometer should be at the same temperature, and if they are not, a correction factor applies. The Marine Insight wording on the correction is unclear, so use the one in your manual.

The article also describes the preparation: stop and cool the engine, remove the cylinder head and piston, cover the stuffing box opening, remove the ridge and clean carbon from the top of the liner, then inspect the surface. Without lifting the piston, a vendor service from HJ Lubricators inserts a gauge through the scavenge ports and reports wear to 1/100 mm. That is the vendor's own claim, and the page gives no measuring levels and does not address ovality.

A Worked Wear Calculation on an 800 mm Bore (Example Readings from a Marine Insight Trade Article, Reproduced as an Illustration)
Port to starboard
Latest reading841.81 mm
Last reading841.45 mm
Wear0.36 mm
Forward to aft
Latest reading841.78 mm
Last reading841.45 mm
Wear0.33 mm
Then divide by the hours
Wear rate per 1,000 running hours is the wear divided by hours run between the two readings, calculated for each level and direction. The article's numbers are an example and give no hours, so we show no rate.
Readings are in millimetres, as given in the article. It labels the difference between the two wear figures, 0.03 mm, as ovality. That is only the difference in wear, so measure ovality from the two diameters at the same level and follow your maker's method.
Keep Every Liner Reading, Hour Count and Photo Against the Right Cylinder Unit
Record each gauging with its levels, directions and running hours, then see the trend before the overhaul list is written.
Free trial available. Or book a walkthrough built around your own engine overhaul and liner wear records.

Cylinder Liner Wear Limits and Rates: What Sources Say and Where They Disagree

Rates per 1,000 hours differ by a factor of several

The published figures are not consistent, and none is from an engine maker's manual. An engine website says about 0.05 mm per 1,000 hours is ideal on a large two-stroke and about 0.015 mm on a medium-speed trunk piston engine. Marine Insight gives about 0.1 mm per 1,000 hours as normal. A vendor's sample gives 0.04 per 1,000 hours on one large engine. These are different engines and conditions, so treat the figures only as a check on whether your own rate looks odd.

Normal Liner Wear Rate Quoted by Different Sources, mm per 1,000 Running Hours (Sources Disagree; Bars to the 0.10 Maximum)
Medium-speed trunk piston engine, ideal (anonymous engine website)

0.015
HJ Lubricators vendor sample on a large engine (48,972 hours)

0.04
Large two-stroke crosshead engine, ideal (anonymous engine website)

0.05
General normal wear (Marine Insight trade article)

0.10
These are not maker limits and they do not agree, partly because they describe different engines and different conditions. The vendor sample is one engine's data with no stated units. Use the engine maker's wear rate and limit, and use these figures only to judge whether a rate looks odd.

Replacement wear as a share of the bore

Marine Insight gives replacement at about 0.6 to 0.8% of the bore diameter or as per the manufacturer, and the engine website gives about 0.8% of the original diameter. Neither gives an ovality limit. The table applies those percentages to common bores by our arithmetic. It shows the scale only, and the engine maker's figure decides when a liner is renewed.

Replacement wear at 0.6 to 0.8 percent of bore: our arithmetic on the percentages quoted by trade sources (for orientation only; the engine maker's limit applies)
Liner bore0.6% of bore0.8% of bore
500 mm3.0 mm4.0 mm
600 mm3.6 mm4.8 mm
700 mm4.2 mm5.6 mm
800 mm4.8 mm6.4 mm
900 mm5.4 mm7.2 mm
980 mm5.9 mm7.8 mm

Reading the wear pattern before you decide anything

Reading the wear pattern: what each pattern suggests and what to check (summarised from trade and maker sources, followed by our suggested action)
PatternUsual suggestionWhat to checkSuggested action
Clover leafing in the lower linerAcid corrosion, worse at low load or with feed rate not matched to loadCylinder oil BN and feed rate against load, drain oil ironReview feed rate against the maker's guidance and sulphur
Heavy wear at the dead centresAbrasion by hard particles such as catalytic finesFuel catfines results, filters and separatorsCheck fuel treatment records
Scuffing or hard contact marksInsufficient lubrication or a ring problemRing condition, feed rate, depositsRaise feed rate as the maker advises and monitor, then plan ring renewal if damaged
Liner polishA risk with some alternating oil practices on low-sulphur fuelsSurface condition and oil strategyFollow the current maker letter, which no longer needs BN alternation with Cat. II BN 40

Scavenge Port Inspection and Piston Ring Checks: What the Maker's Letters Ask For

A cadence from fortnightly drain oil checks to the yearly measurement

The maker letters are the most authoritative sources here, but they apply to MAN B&W two-stroke engines and have been updated. SL2019-671 of April 2019, SL2023-737 of June 2023 and Everllence's SL2025-776, as reported by CMT in February 2026, move in the same direction: inspect often, change the feed rate in small steps and read the drain oil in context. Piston ring inspection is part of the same visit, with the 2019 letter asking for ring coating thickness and pressure relief grooves to be measured and cermet coating fitted on all piston rings and piston cleaning rings for VLSFO and ULSFO operation.

A Liner Condition Monitoring Cadence Built from Maker and Trade Sources (Our Summary; the Engine Maker's Manual for Your Engine Sets the Intervals)
14 days to monthlyScavenge drain oil samples, with values averaged over 2 or 3 samples (MAN 2019 letter). Onboard kits can supplement laboratory analysis
MonthlyScavenge port inspection of cylinder condition (MAN 2019 and 2023 letters), more often when reducing feed rate
Every two weeksPort inspection when ring land deposits are heavy (MAN 2019 letter)
1,500 hours or 3 monthsScheduled laboratory drain oil analysis (Everllence SL2025-776, as reported by CMT)
At least yearlyLiner wear measurement (MAN 2019 letter)
Unit overhaulFull gauging when the unit is opened. One engine website cites a 15,000 running hours overhaul for its example
The MAN letters apply to MAN B&W two-stroke engines. The company now trades as Everllence. Intervals for other makes and for four-stroke engines must come from their own manuals, and we found no four-stroke maker figures.

Cylinder Oil Feed Rate and Drain Oil Analysis: The Numbers in the Maker Letters

Feed rate figures and iron limits, with the caution that context matters

The table collects the figures from the two MAN letters. They apply to MAN B&W two-stroke engines and may have been superseded by the letter in force for your engine. Read them as a record of how the guidance is framed: a minimum feed rate, a safe setting to return to, small reduction steps and a requirement that cylinder condition is good before each cut.

Cylinder lubrication figures from the MAN service letters (SL2019-671, April 2019, and SL2023-737, June 2023; two-stroke engines; read the current letter for your engine)
ItemFigure in the letterLetter
Absolute minimum feed rate0.60 g/kWh2023
Normal feed rate0.6 to 0.8 g/kWh fixed pitch, 0.8 g/kWh controllable pitch2023
Maximum continuous feed rate1.5 g/kWh at MCR2023
Step when reducing feed rate0.05 to 0.1 g/kWh, only after confirming good cylinder condition2023 (0.1 in 2019)
Safe setting if consumption is low1.2 g/kWh, then investigate2023
Oil for fuels at or below 0.50% sulphurCat. II BN 40 on newer engines (Mk. 9 and later) and dual-fuel engines2023
Oil for fuel above 0.50% sulphurCat. II BN 100 to 140 or above on Mk. 9 and later2023
Drain oil iron limit, 26 to 50 bore100 ppm2019
Drain oil iron limit, 60 to 70 bore150 ppm2019
Drain oil iron limit, 80 to 98 bore200 ppm2019
Drain Oil Total Iron Limit by Bore Group in the 2019 MAN Letter (ppm; Bars to the 200 ppm Maximum; Limits Should Be Adjusted to Each Engine's Measured Wear)
26 to 50 bore

100 ppm
60 to 70 bore

150 ppm
80 to 98 bore

200 ppm
The 2023 letter replaces the 2019 one. It stresses evaluating drain oil in context and the 2025 Everllence letter, as reported by CMT, warns that iron must be corrected for feed rate and dilution, so a number inside a limit is not proof of low wear. We quote the 2019 limits as history, and you should use the letter in force.

A number inside a limit is not proof of low wear. Everllence's 2025 guidance, as reported by CMT, says iron should be corrected to a reference feed rate and read alongside fuel sulphur and residual base number, and that system oil dilution can lower both iron and BN readings. Keep the drain oil results, the feed rate and the fuel sulphur on one record, with the preventive maintenance schedules showing the next scavenge inspection and drain oil sample. Spare liners, rings and gauges can sit in the spare parts inventory.

Cylinder Liner Wear Measurement Checklist: Ten Cards With a Checkpoint Type

Calibration, inspection and records, each marked Visual, Test or Record

Use the cards at each gauging and port inspection. They are our template and do not replace the engine maker's overhaul instructions.

TestGauge and tool check

Internal micrometer checked against a standard, template bar clean and the right one for the unit.

TestTemperature equalised

Liner and micrometer at the same temperature, or the correction applied and recorded.

RecordSame points, same directions

Port to starboard and forward to aft at the same marked levels as the last reading.

RecordHours between readings

Running hours since the last gauging recorded for every unit, so wear rate per 1,000 hours can be calculated.

VisualScavenge port inspection

Ring pack clean and free, no hard contact marks, ring land deposits noted, photographs dated.

VisualLiner surface

Scuffing, polish, clover leafing or ridging noted, with the cylinder unit and position.

TestRing coating and grooves

Ring coating thickness and pressure relief grooves measured when rings are out, as the 2019 letter asks.

RecordCylinder oil feed rate

Actual consumption against the maker's figure, and any change and its reason, recorded.

RecordDrain oil results

Iron, residual BN and fuel sulphur on the same record, with the feed rate they relate to.

RecordOverhaul record

Parts renewed, clearances and measurements filed against the unit for the next gauging.

Seven Ways Liner Wear Records Go Wrong

Why a measurement is hard to use later

1
Using different measuring points each timeThe readings only compare if the levels and directions match the last set. A template bar with drilled holes, as one engine website describes, fixes the points.
2
Measuring a warm liner with a cool micrometerBoth sources tell you to equalise the temperature or apply a correction. Record which you did.
3
Reading the iron number aloneThe 2025 Everllence guidance, as reported, says low numbers alone are not enough, and that uncorrected iron can mask actual wear rates.
4
Cutting the feed rate without a good inspectionThe MAN letters say to reduce the feed rate in small steps, and only after inspection shows good cylinder condition.
5
Skipping the scavenge port lookThe letters recommend monthly inspections, and every two weeks when ring land deposits are heavy.
6
Recording the result but not the hoursWithout hours run, wear cannot be turned into a rate, and a rate is what shows an abnormal trend.
7
Keeping each overhaul record in a different placeA liner decision needs the whole history in one place, including the scavenge port photographs and drain oil results.

Keeping Liner Readings, Photos and Overhaul History in One Place

How a dated photo repository, task ownership and deadlines support liner condition decisions

Liner decisions need history that survives crew changes. Marine Inspection supports a dated photo repository, observations turned into tasks with owners, deadlines and evidence, and certificate and equipment tracking. A dated scavenge port photograph for every cylinder, a task for a hard contact mark with a named owner and a due date, and each gauging stored against the unit with its hours give a Chief Engineer and a superintendent the same picture. It does not replace the engine maker's manual or class requirements. Raise the follow-up jobs through maintenance work orders and see Marine Inspection pricing for plans.

Frequently Asked Questions About Cylinder Liner Wear Measurement

How is cylinder liner wear measured?

Gauge the bore with an internal micrometer at fixed levels down the liner, port to starboard and forward to aft, with the liner and micrometer at the same temperature, and compare each reading with the last set. Divide the wear by the running hours between readings to get a rate per 1,000 hours. Your engine maker's manual sets the levels.

What is the wear limit for a cylinder liner?

Trade sources quote about 0.6 to 0.8% of the bore diameter, or the maker's figure, for replacement. That is roughly 4.8 to 6.4 mm on an 800 mm bore by our arithmetic. Neither source is a maker's manual, so use your engine maker's limit.

What is a normal liner wear rate?

Sources disagree. One engine website calls about 0.05 mm per 1,000 hours ideal on a large two-stroke and 0.015 mm on a medium-speed engine, and a trade article gives about 0.1 mm per 1,000 hours as normal. Use your maker's rate and watch for a change in your own trend.

How often should liner wear be measured?

MAN Energy Solutions' 2019 letter for MAN B&W two-stroke engines recommends measuring liner wear at least once a year, with monthly scavenge port inspections. One engine website describes gauging at a 15,000 running hours unit overhaul. Other makes and four-stroke engines follow their own manuals.

What should I look for in a scavenge port inspection?

Look at the ring pack for cleanliness and free movement, hard contact marks, ring land deposits and the liner surface. The MAN letters give actions for hard contact marks, such as raising the feed rate to 1.2 g/kWh and planning ring renewal if rings are damaged, and recommend photographs be kept.

How does cylinder oil feed rate affect liner wear?

A feed rate too low risks scuffing and a mismatch with load or fuel sulphur can allow corrosion. The 2023 MAN letter gives a 0.60 g/kWh minimum and a 1.5 g/kWh maximum continuous rate for its engines and says to reduce in 0.05 to 0.1 g/kWh steps only after a good inspection.

What records should be kept for liner wear?

Keep every measurement with its date, levels, directions, temperature and running hours, scavenge port photographs, drain oil results with the feed rate and fuel sulphur, and the overhaul record for each unit. The trend over several gaugings matters more than any single reading.
Arrive at the Overhaul With Every Liner Reading and Port Inspection Already Trended
Gauging records, scavenge port photographs, drain oil results and follow-up tasks for every cylinder, in one system.
Free trial available. Or book a walkthrough built around your own engine overhaul and liner wear records.