A good SEEMP Part III is not a binder that sits on the bridge. It is a three-year promise that the ship's attained CII will stay at or below the required value, written so that a verifier can check it and a crew can follow it. The reduction factor tightens each year, so a plan that was comfortable in year one can look thin by year three. This guide covers what the plan contains, when a corrective action plan is triggered, how verification works and how to keep the audit trail in one place. For tracking attained CII between reports, see our CII carbon intensity tracking software guide.

ABCDE
Write a SEEMP Part III That Survives Verification
CII targets, corrective action plans, monitoring and the evidence trail that flag states and verifiers expect each year.
Free trial available. Or book a walkthrough built around your own SEEMP Part III actions.
5,000 GT
Size threshold
The CII framework applies to ships of 5,000 GT and above, as covered in the sources we read.
D x3 or E x1
Corrective plan trigger
A D rating three years running, or one E rating, requires a corrective action plan.
1 month
Time to submit the plan
At most one month after the attained CII is reported (IACS Rec. 175).
21.5%
2030 reduction factor
Versus 11% in 2026, per our reading of MEPC.400(83).

What SEEMP Part III Is and Where It Sits in the Plan Structure

Why Part III exists and how it links to Part I and Part II

IACS Recommendation 175 describes Part III as an implementation plan on how the attained annual operational CII is kept at or below the required CII for three years, and it covers the data needed for the CII calculation. Part II covers the Fuel Oil Data Collection System methodology, and Part I holds the general ship energy efficiency measures. The recommendation says the Part I sections on Measures, Monitoring, Goal and Evaluation should be revised to match Part III, so the three parts do not contradict each other.

Which regulations sit behind the plan and why the format matters

The regulatory basis in the sources we read is MARPOL Annex VI, with the plan format set out in Appendix 2bis of resolution MEPC.346(78), as amended. IACS says the plan must follow that format. A plan that is thoughtful but in the wrong layout can fail at the first check, so start from the official template rather than a blank page. For the related design-side requirement on existing ships, see our {L2}.

Setting CII Targets: Required Values, Rating Bands and the Tightening Curve

How the reduction factor tightens the required CII every year

The required CII falls as the reduction factor rises. We read MEPC.400(83) as setting 11% for 2026 and 21.5% for 2030. The chart shows the selected years we could confirm. Plan for the value of the year you are in and the years ahead, not for last year's figure, and leave a required-CII cell blank where a factor has not been set, as IACS Rec. 175 section 4.1 allows.

The Reduction Factor Keeps Rising: Required CII Falls Every Year (Selected Years)
2023

5%
2024

7%
2025

9%
2026

11%
2030

21.5%
Reduction factors relative to the 2019 reference. 2023 to 2025 values are from the original CII reduction schedule as we recall it; 2026 and 2030 are from MEPC.400(83) as we read it. We did not verify 2027 to 2029, so they are left out. Check the resolution text before using any figure in a plan.

How the rating bands are built around the required value

Ratings run from A, a major superior performance, to E, inferior. Rating C is the middle band and is tied to the required annual CII. The Dromon publication says the boundaries are the required CII multiplied by exponential transforms of the d vectors, and gives bulk carrier multipliers of 0.86, 0.94, 1.06 and 1.18. It also says a ship's rating depends on its own attained CII and the fixed boundaries, not on other ships' results. That makes the target setting a matter of your own data, not a race against the fleet.

How a Rating Is Set: Bulk Carrier Example Boundaries Around the Required CII (Dromon Worked Example)
Abelow 0.86
B0.86 to 0.94
C0.94 to 1.06
D1.06 to 1.18
Eabove 1.18
Multipliers of the required CII for bulk carriers, from the Dromon technical publication (2022). With a required CII of 10, the boundaries are 8.6, 9.4, 10.6 and 11.8, so an attained CII of 9 is rated B. Band widths here are drawn for readability, not to scale. Other ship types have other multipliers.
Keep Every CII Action With an Owner, a Deadline and Evidence
Turn each measure in your plan into a task that has a named person, a date and a photo or record attached when it closes.
Free trial available. Or book a walkthrough built around your own SEEMP Part III actions.

Building the Three-Year Implementation Plan: Measures, Impact and Responsibility

What each year of the plan should show

The Dromon template includes a table of the targeted annual CII and rating for each of the next three years, and an impact on CII column for every measure. IACS Rec. 175 requires measures that are effective enough to achieve the required CII with reasonable assurance, and a planned self-evaluation. The layout below is our illustration of how to organise those elements. The boxes hold placeholders, not real figures.

A Three-Year Implementation Plan Layout: Target and Rating Per Year (Our Illustration, No Real Figures)
YEAR 1
Required CII: from the schedule
Targeted annual CII: your figure
Targeted rating: C or better
Measures starting: listed
YEAR 2
Required CII: tighter
Targeted annual CII: your figure
Targeted rating: C or better
Review point: mid-year
YEAR 3
Required CII: tighter again
Targeted annual CII: your figure
Targeted rating: C or better
Revise before year end
The Dromon template has a table for the targeted annual CII and rating for each of the next three years, and an Impact on CII column for each measure. IACS Rec. 175 says Part III should be revised before the end of the last year of the plan. The values in the boxes are placeholders for you to fill in.

Which measures the sources name and how to keep proof that each one was done

The Dromon publication gives only a short list of examples: hull cleaning to reduce drag, speed and routeing optimisation, low-energy lighting, and solar or wind auxiliary power for accommodation services. It gives no numeric impact figures for individual measures. So the effect of each measure must come from your own data and engineering judgement, labelled as an estimate. The table pairs the named examples with evidence you could keep. The evidence column and the last two rows are our suggestions.

Typical measure families and how to evidence them (examples named in the sources, plus our suggested evidence)
Measure familySource of the exampleEvidence to keep (our suggestion)Checkpoint type
Hull cleaning to reduce dragDromon technical publicationDated before and after photos, cleaning report and dateRecord
Speed and routeing optimisationDromon technical publicationVoyage plan notes, speed orders and the fuel recordRecord
Low-energy lightingDromon technical publicationFitting list, dated photos of the installed unitsVisual
Solar or wind auxiliary powerDromon technical publicationInstallation records and commissioning testTest
Engine and propeller conditionOur suggestion, not from the sourcesCondition survey and performance dataTest
Operating practice and crew awarenessOur suggestion, not from the sourcesBriefing records and standing order sign-offRecord
Examples are from the Dromon technical publication (2022). Evidence and the last two rows are our suggestions. We did not find quantified savings in the sources, so none are shown.

Corrective Action Plans: Triggers, Content and the One-Month Deadline

Which ratings trigger the plan and what is said about the sequence

IACS Rec. 175 says a corrective action plan is required if a ship is rated D for three consecutive years or E for one year. The revised Part III with the plan goes to the Administration or an authorised organisation for additional verification. The plan aims to meet the required CII in the second year after the year being rated, and it should be verified in the year between. Check the exact wording against the regulation for your case.

When the Corrective Action Plan Is Triggered (Our Simplified Diagram)
Path 1
Year 1: D
Year 2: D
Year 3: D
Plan required
Path 2
Any one year: E
Plan required
No trigger
A, B or C
D then C
Keep monitoring
Trigger rule: D for three consecutive years or E for one year (IACS Rec. 175, sections 6.1 and 7.3). The consecutive-years wording is as we read it; check the regulation for how a break in the sequence is treated.

What the plan should contain and what verifiers check

Dromon says the plan should list the actions, their timeline and their expected impact on the CII rating, name the company personnel responsible, and describe possible impediments and contingency measures. IACS adds a root cause analysis and self-evaluation. Additional verification checks that the plan is necessary, follows the Appendix 2bis format, has sensible timelines, is effective, and that the company can carry it out.

What a Corrective Action Plan Should Contain (Dromon and IACS Rec. 175 Guidance, Our Grouping)
Root cause analysis
Why the rating fell short, before choosing any fix (IACS Rec. 175, 6.6).
Measures and timing
A list of measures, when each starts and how it will be implemented.
Expected CII impact
How the measures together reach the required CII, with impact stated per measure.
People responsible
Company personnel for the plan and for monitoring it.
Impediments and fallback
Possible obstacles and contingency measures.
Self-evaluation
A planned review of progress, with adjustments when needed.
Dromon says the plan should be ship-specific and SMART where feasible. IACS Rec. 175 says actions should be achievable, measurable and time bound. Follow the Appendix 2bis format in MEPC.346(78), as amended, for the actual plan.

Verification, Confirmation of Compliance and the Annual Reporting Clock

How initial, periodical and additional verification differ

Initial verification checks compliance with regulation 26.3.1 and results in a Confirmation of Compliance kept on board. Verification is based on documentary evidence. Periodical and additional verifications have their own document sets in sections 7.2 and 7.3 of the recommendation, and each requires re-issue of the CoC. Once the plan is verified and the CoC re-issued, the Administration or recognised organisation can issue the Statement of Compliance.

The Annual Reporting Clock Around SEEMP Part III
BY 31 MARCH
Report attained CII
Submit for verification (Dromon).
WITHIN 1 MONTH
Submit the revised plan
Only if D x3 or E. The deadline runs from reporting.
BY 31 MAY
Statement of Compliance
A non-acceptable plan leads to no SoC before 31 May (IACS Rec. 175).
BY 30 NOV
Company audits, if conducted
Dromon date for any audit of the plan.
Dates from the Dromon technical publication and IACS Rec. 175. Your flag or class may add its own steps. Confirm with them.

What to keep on board so the documents are ready

IACS recommends submitting the latest verified Part II and, if referred to, the latest Part I with the Part III. Keep both with the CoC and the latest CII report, and keep the monitoring records they rely on. The checklist below is our suggested template and should be adapted to your flag and class.

The SEEMP Part III Readiness Checklist: Plan, Data and Evidence

A checklist with a checkpoint type on each item for the superintendent and the compliance manager

Work through the table before each annual report and before the plan is revised. Items marked Record are about documents, Visual about what you can see on board, and Test about a check that proves something works.

SEEMP Part III readiness checklist, with a checkpoint type on every item (our suggested template)
ItemWhat to checkCheckpoint type
Required CII for each yearEntered from the current reduction factors, with blanks left where factors are not yet setRecord
Part II methodologyVerified SEEMP Part II on board, since initial verification requires itRecord
Part I alignmentPart I Measures, Monitoring, Goal and Evaluation sections revised to match Part IIIRecord
Appendix 2bis formatPlan follows the format in MEPC.346(78), as amendedRecord
Measure effectivenessMeasures are enough to reach the required CII with reasonable assuranceTest
Self-evaluationReview dates set and an owner namedRecord
Confirmation of ComplianceCoC on board after satisfactory verificationVisual
Monitoring dataFuel, distance and speed records trace back to the data collection systemTest
Our suggested template. Checkpoint types: Visual, Test and Record.

Tracking Actions With a SMART Layout So Nothing Slips Between Reports

How to turn the plan's measures into rows someone owns

Both Dromon and IACS call for actions that are specific, measurable, achievable, time bound, and where possible realistic. A table with the fields below turns each measure into a row with an owner, a deadline and a place for evidence. The layout is our illustration, not a prescribed format.

A SMART action tracker row layout for the plan (our illustration)
FieldWhat goes in itWhy it helps
ActionOne measure, written so one person can own itSpecific
Measure of successThe number that will change and how it is readMeasurable
OwnerA named company person, not a departmentAccountable
DeadlineA calendar date inside the three-year periodTime bound
EvidencePhoto, record or report attached when closedVerifiable
Expected CII impactYour estimate, labelled as an estimateHonest forecast
Our illustration. The official plan must follow Appendix 2bis of MEPC.346(78), as amended.

Mistakes That Leave a SEEMP Part III Weak at Verification

Six habits that turn a three-year plan into an audit finding

1
Treating Part III as a one-off document
It is a three-year plan that is monitored and adjusted, and must be revised before the end of its last year (IACS Rec. 175).
2
Waiting for a bad rating before planning
The corrective plan is due within one month of reporting. Starting then leaves little room for root cause work.
3
Measures with no number attached
Dromon asks for the impact on CII per measure. A list of intentions does not show that the required CII will be met.
4
No owner on each action
The plan must name the company personnel responsible. Shared ownership usually means none.
5
Forgetting Part I and Part II
Part I sections should match Part III, and a verified Part II is needed for initial verification.
6
Evidence kept on one laptop
Verification is documentary. Scattered files and photos weaken the audit trail.

Systems That Keep CII Actions, Evidence and Dates Together

How a dated photo repository, task ownership and deadlines support the audit trail

SEEMP Part III depends on actions being done and proved. Marine Inspection supports a dated photo repository, observations turned into tasks with owners, deadlines and evidence, and certificate and equipment tracking. A dated photo of a cleaned hull, a task for each measure with a named owner, and a tracked Confirmation of Compliance give a verifier an organised record. This does not replace the verified plan or the class or flag process. It keeps the supporting evidence findable.

Frequently Asked Questions About SEEMP Part III

What is SEEMP Part III?

It is the part of the ship energy efficiency management plan that sets out a three-year implementation plan for keeping the attained annual operational CII at or below the required CII, along with the data needed to calculate it (IACS Rec. 175, section 2.3).

When is a corrective action plan required?

When a ship is rated D for three consecutive years or E for one year. The revised Part III with the plan goes to the Administration or an authorised organisation for additional verification.

How long do we have to submit the plan?

In no case later than one month after reporting the attained annual operational CII (IACS Rec. 175, section 6.3).

What does verification involve?

It is based on documentary evidence. Initial verification checks compliance with regulation 26.3.1 and results in a Confirmation of Compliance kept on board. The recommended documents include the latest verified Part II and, if referred to, Part I.

What happens if the plan is not accepted?

IACS Rec. 175 notes that a non-acceptable plan leads to non-issuance of the Statement of Compliance before 31 May. Check with your flag or class for how this is handled.

When must Part III be revised?

Before the end of the last year in the three-year plan. Changes to the company, flag or measures can also trigger re-verification (IACS Rec. 175, section 7.2).

Are the rating boundaries the same for every ship?

No. They are the required CII multiplied by factors that depend on ship type. The Dromon bulk carrier example uses 0.86, 0.94, 1.06 and 1.18. Look up the factors for your own ship type.
Be Ready Before the Annual CII Report Is Due
Measures, owners, deadlines and evidence for every ship in one system your superintendents and compliance team can use.
Free trial available. Or book a walkthrough built around your own SEEMP Part III actions.